Sunday, July 30, 2023

Bathroom pt 6

 Progress continues, slow but steady...  Hard to get a lot done 2 days at a time, when your family enjoys your company as well 😁

I was able to get some drywall and durock up.  I used my left over thinset from filling in hole and tried to tuck point the cinderblock wall a bit as well.

Looks like the lights were installed as well.  I forgot to mention a spend a good chunk of time vanishing the ceiling as well, before the show pan went in.  I had a good respirator for that, and I am glad that I did, because it made the entire cabin stink for a day or 2 after!



Sunday, July 23, 2023

Bathroom pt 5

 Another weekend some more progress.  I was able to get the hole drilled for the vent, install the sliding door, and get the shower pan installed (with the issues I mentioned in the last post).




Wednesday, July 19, 2023

A playset for Kit

My niece is coming to live at my Mom's cabin this fall.  My Mom found a playset on marketplace and recruited us to pick it up and install it at the cabin.  Our trailer handled it well and we were able to get it up and running in short order.


 

Sunday, July 16, 2023

Bathroom pt 4

 I was able to finish up most of the ceiling, and I put down self-leveling concrete in the shower pan.  However, self-leveling is a bit of a misnomer.  It looks really smooth and level, but it isn't 100% level there is probably at leave a 1/4 to 1/2 difference in some places...

I put some glue on the fins of the shower pan, but it didn't fix it entirely and the pan will squeak a bit here and there.  I may try to spray some foam under it, but it will probably not work well, since there are fins in the way...  If I could start over I would put down a bed of mortar, or make sure it was really level.



Saturday, July 8, 2023

Bathroom pt 3

 As I was waiting for the concrete to dry, I started working on the ceiling.  Greg has a bunch of cedar he had planned to use for a sauna, but it worked really well as the ceiling in the bathroom as well.


I would end up regretting just putting the wood in there like that, as they were not easy to remove.  However, they did get the job done.

Friday, July 7, 2023

Bathroom pt 2

 I was eventually able to get the old plumbing out, I tried heat, that didn't work and probably wasn't too healthy...  The I used a reciprocating saw and cut off the trap, so I could use some drill bits and drill out the lead/oakum.  Eventually I was able to wiggle it out.


That is a lot of years of built up hair in the drain, amazing that it worked at all!

There is a rubber gasket that goes into the iron pipe, then this goes in and we start the looping.

I thought about putting the trap coming right out of the iron drain, but the guy at Ace said it would be best to have it right under the drain and it worked well like that.  Overall very happy with how it all turned out.  It seems to be draining well, and hopefully will be for a long time!

Wednesday, July 5, 2023

To redo a basement bathroom at the Cabin

 I am writing this on October 30th, because I wanted to finish the bathroom before I posted about it.  It is somewhat done at this point.  We did the demo on this day.  We had been up since Friday, but had played a lot!  Leading up to this, I had taken out the toilet, sink, drywall, and rewired for the new location of the switches.  But we had held off on the shower till now, since it is the only one!



That is the before.  We accomplished quite a bit that first day!


Then I saw this!